A product owner has the Developers write most Product Backlog items, because they understand the technical detail better. A stakeholder objects that the product owner is not doing their job. What is the correct position?

Written from the published competencies and the Scrum Alliance CSPO Learning Objectives and the Scrum Foundations Learning Objectives, which draw on the 2020 Scrum Guide, the Manifesto for Agile Software Development and the Scrum values. Not actual exam questions, and not affiliated with or endorsed by Scrum Alliance.