During a Sprint Retrospective, a developer says the Sprint Goal was unrealistic from the start but nobody said so at Sprint Planning because the Product Owner had already told stakeholders it would be met. Which two Scrum Values are most directly at issue?
Written from the published competencies and the Scrum Alliance CSPO Learning Objectives and the Scrum Foundations Learning Objectives, which draw on the 2020 Scrum Guide, the Manifesto for Agile Software Development and the Scrum values. Not actual exam questions, and not affiliated with or endorsed by Scrum Alliance.