Schedule management

A schedule is a model of how the work will unfold in time, built from activities, the order in which they can happen and how long each takes. Schedule is one of the seven performance domains in PMBOK 8, and the examination tests it through network diagrams, float arithmetic and scenarios in which a date has to be brought forward. The dates a schedule prints are the least of it. Its value is the structure underneath, which shows which delays matter and which do not.

Most of what a schedule can say comes from the relationships between activities, and the durations come second. A network that is wrong makes every date derived from it wrong, and no estimating accuracy rescues it. The sections below cover the dependencies a network is built from, leads and lags, the critical path, float, the two ways a schedule is compressed and how far ahead detail is worth writing.

Sequencing and the four kinds of dependency

Activities are joined by logical relationships, each named for which end of the predecessor governs which end of the successor.

Finish to start is the common one, where the successor cannot begin until the predecessor finishes. Start to start lets the successor begin once the predecessor has begun, which is how paving follows grading down a road at a fixed distance behind. Finish to finish means the successor cannot complete until the predecessor does, which fits testing that has to close out alongside the writing it inspects. Start to finish is rare, since the successor cannot finish until the predecessor starts, and its standard illustration is a shift that must begin before the outgoing one may end.

Dependencies are also classified by where the constraint comes from. Mandatory logic is inherent in the work, since concrete has to be poured before it can cure. Discretionary logic is a preference drawn from practice, and it is the first place to look when compressing a schedule. External logic sits outside the project, such as a regulator's approval date, while internal logic is under the project's control.

Lead and lag

A relationship can also carry an offset. A lead lets a successor start before its predecessor finishes, so a finish to start relationship with a five day lead begins the successor five days early. A lag inserts waiting time, such as the fortnight concrete needs to cure.

Neither is padding. A lag is a property of the work and belongs in the network. A margin added because somebody is nervous belongs in a reserve where it can be managed.

The critical path

Once the network is built, the critical path can be read from it. The critical path is the longest path through the network, and because every activity on it must happen in sequence, it is also the shortest possible duration for the project. Those two statements sound contradictory and describe the same fact.

Path totalA5 daysB7 daysE6 daysC4 daysF5 daysD3 daysG2 daysH4 days22 dayscritical path18 days4 days of float14 days8 days of floatEvery path starts at A and finishes at H, so the project cannot finish in less than 22 days

The path through B and E runs to 22 days, which fixes the project duration and leaves that path with no room at all. The path through C and F takes 18 days, so the four days between it and the critical path are the float shared along it, and the path through D and G carries eight.

Position in the logic is the whole of it. An activity is critical because everything downstream waits on it, which has nothing to do with how difficult or how valuable the work is. There may be more than one critical path, and a project carrying several is more fragile, since a delay on any of them moves the finish date.

Total float and free float

The other paths in the diagram have room in them, and that room is float. Total float is how long an activity can slip without delaying the project finish. Free float is how long it can slip without delaying any immediate successor, which is a tighter and more local number.

Activities on the critical path have zero total float by definition. Where a schedule shows negative float, the network is reporting that the imposed date cannot be met with the logic and durations as they stand, so something has to change, and working harder against the number is no answer.

Float belongs to the path. Two activities in sequence sharing ten days of float have ten days between them, which is why consuming it early leaves nothing for later. The network above shows the same arithmetic at a readable size. Both C and F report four days of total float, and the path they sit on carries four days in total, so C slipping by three leaves F with one. Spending float is a decision taken on behalf of everything downstream.

Crashing and fast tracking

When the critical path is longer than the date allows, two techniques compress it, and they trade different things. Crashing adds resources to activities on the critical path, so it buys time with cost. It works only where an activity responds to more people, and it meets diminishing returns quickly.

Fast tracking runs activities in parallel that were planned in sequence, so it buys time with risk. Starting construction on a design that is eighty per cent settled means some of it may be undone when the last fifth arrives, and rework is the price of the overlap.

TechniqueWhat it doesWhat it costsWhat it risksWhen it fits
CrashingAdds resources to activities on the critical path so each takes less timeMoney, and usually more than proportionally, since the fourth engineer adds less than the secondCoordination overhead, quality slipping as people join late, and a new critical path appearing elsewhereThere is budget to spend, and the activity genuinely responds to more people
Fast trackingOverlaps activities that were planned in sequence, so the successor starts on partial informationNothing directly, which is what makes it temptingRework when the predecessor changes after the successor has started, and a much busier set of dependencies to manageThere is tolerance for rework, and the logic being overlapped is discretionary, since mandatory logic cannot be overlapped

The network above shows where either technique is worth applying. Adding people to C or D buys nothing at all, because those paths already carry float, and the only compression that moves the finish date is compression on A, B, E or H.

Neither produces time from nothing. Every compression technique trades one constraint for another, and a plan that shortens without conceding cost, risk or scope has usually moved the optimism somewhere less visible.

Rolling wave planning

Compression is a decision about near work, and the far future is treated differently. Detailed planning is done for imminent work and left deliberately coarse further out, with detail added as the horizon approaches. Planning packages hold the coarse portion until it is decomposed.

The coarseness is the rigour. Detail written about work eighteen months away will be rewritten before anybody uses it, so the effort is spent twice. The same reasoning underlies adaptive planning, which is why hybrid projects sit comfortably with a milestone schedule above short cycles.

Common misconceptions

“The critical path is the sequence of the most important activities.”

It is the longest path through the network, and therefore the shortest possible project duration. An activity is on it because of its position in the logic, so a trivial activity everything waits on is critical while a demanding one with room around it is not.

“Fast tracking and crashing are two names for speeding a project up.”

Crashing adds resources to critical activities and buys time with cost. Fast tracking overlaps activities that were sequential and buys time with rework risk. Which one fits depends on whether the budget or the risk tolerance has room in it.

Where this is examined
PMP
Process, 41 per cent of the exam.
Related material
Book
Critical Chain, On float, buffers and where safety margin actually goes.
Book
The Principles of Product Development Flow, On queues and why loading a plan to capacity lengthens everything.
Book
How Big Things Get Done, On schedule overrun as a pattern rather than an accident.