A satellite ground station upgrade covers three components. The antenna assembly has an 11 month tooling lead and a late design change scraps a mould. The scheduling software has requirements the operators cannot describe until they use it, and those operators sit in the same building. The archive migration reveals more about the source data with every trial run. The sponsor asks the project manager to state whether the programme is predictive or agile. What is the best response?
- ARun the whole programme predictively, because the antenna carries most of the budget and a single approach keeps reporting consistent.
- BRun the whole programme adaptively, since the organisation has adopted an agile operating model.
- CDefer the decision until the requirements for all three components are stable enough to plan.
- DChoose the approach for each component at the level where the risk sits, and hold them together with an integration plan and a shared view of dependencies.