The relationship between a product vision and a Product Goal, creating a Product Goal and a Sprint Goal, the components of a product plan or forecast, planning a release, and identifying small, valuable and usable increments.
A CSPO course asks you to explain the relationship between a product vision and a Product Goal. Which explanation is correct?
AThey are two names for the same statement, one used internally and one externally.
BThe Product Goal is set first and the vision is derived from it once several goals have been achieved.
CThe vision is a Scrum artifact and the Product Goal is a stakeholder document.
DVision describes the long term future state of the product. The Product Goal is the single objective the Scrum Team is currently working toward on the way there, and it lives in the Product Backlog as its commitment.